| January - 2007 |
February - 2007 |
|
Beginning of excavations of the large earth water dam, next to the recovery plants. |
|
Repairs to two of our 4X4 vans, before exploration expedition. |
| March - 2007 |
April - 2007 |
|
Construction of the foundations of the new scrubber and Knelson MD 12 Base |
|
The 'Tamil' fully operational, preparing soil feed of 1.5mm diameter. For the Knelson concentrator. The conveyor of the crusher and milling machine assisting, during our test runs. |
| May - 2007 |
June - 2007 |
|
Scrubber dram and frame 90% completed by Page Engineering. |
|
The construction of a black sand machine for the laboratory to tread gold concentrate, by Page Enginnering. |
| July - 2007 |
August - 2007 |
|
The GM-1 Machine fine tuned and the feeding rumps are completed. the plant will undertake a number of test runs in a couple of days. |
|
Phase - A of the gold recovery plant is ready and tested, recovery 75%. additional adjustments will be undertaken to improve the gold recovery rate. |
| September - 2007 |
October - 2007 |
|
Scrubber and Knelson platforms (4m high) and rumps completed in concrete construcion. |
|
The construction of the propeller of the agitator tank for the gold concentrate, feed to the shaker table, by Page Enginnering. |
| November - 2007 |
December - 2007 |
|
Electrification of the complete site of Dabale-1, for the future night operating production shifts. |
|
Night Production test run of the gold recovery equipment. While you doing fine tune adjustments you covered in mad. Well done Costa and Vince. |