| January - 2008 |
February - 2008 |
|
Page Engineering, in assisting local villagers with general repairs regarding their transportation and other equipment, free of charge, as part of Page Mali's social program and responsibility. |
|
Page Enginnering in manufacturing of all Steel windows doors and general ironmongery for the new buildings. |
| March - 2008 |
April - 2008 |
|
Page Engineering testing crushing and milling equipment after various adjustments for better performance. |
|
Delivery of farming planting equipments presented to the chiefs of the villages around Dabale-1 gold mine, as part of Page Mali's social program. |
| May - 2008 |
June - 2008 |
|
Abaladougou Kenieba visit from the technical group of ARH with their specializing geologists and management for the evaluation of Dabale-1 gold mine and due diligence. |
|
Presentation by Page Mali administration in DNGM (Mali Ministry of Mines and Energy) offices, for the application of small Scale gold mine license. |
| July - 2008 |
August - 2008 |
|
Gold recovery from a new test pit hole sample. The laboratory indicated the purity to be 21.9 carats and a number of samples tested by independent ALS laboratory indicate the grade of 19 g/t in a depth of 25 meters. |
|
Planting various plants as part of the environmental program in conjuction with PAge Mali's social responsibility. |
| September - 2008 |
October - 2008 |
|
Second visit from ARH in the Abaladougou Kenieba gold concession, for additional verification and sample taking and analysis including field exploration for the satellite interpretation. |
|
Manufacturing on site for concrete blocks for the construction of additional buildings and clinic. |
| November - 2008 |
December - 2008 |
|
Commencement of foundation construction for additional ablution block, kitchen and store rooms. |
|
Construction of Dabale-1 site additional accommodation and clinic brick work. |